Customer/Agency |
Department of Commerce, National Oceanic and Atmospheric Administration |
Location |
Oxford, MD |
Project Type |
Design/Build Renovation Servicess |
Contract Value |
$132,000 |
Contract Number |
WC133C-09-SE-4409 |
CFM Project
Manager |
Mr. Tim Stufft |
CFM Construction Manager |
Mr. Bill Booth |
Project Title |
Necropsy Laboratory Design/Build Renovation |
Description of Project |
CFM Engineering provided all design, engineering, labor, materials, Project and Construction Management services for interior renovation of the Necropsy Laboratory. Project scope includes demolition, interiors, laboratory equipment including fume hoods, and commissioning services. |
Period of Performance |
In-Progress |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
| |
Customer/Agency |
Smithsonian Institute, Washington DC |
Location |
Arts & Industries Building |
Project Type |
Renovation/Construction Services |
Contract Value |
$243,000 |
Contract Number |
F07CC10283 |
CFM Project
Manager |
Mrs. Nancy Fitzgerald |
CFM Construction Manager |
Mr. Michael Schumacher |
Project Title |
AIB Moves to QUAD |
Description of Project |
CFM Engineering provided all labor, materials, Project and Construction Management services for Interior Office Space Renovations. Project scope included all walls, flooring, fire alarm systems, and electrical systems. |
Period of Performance |
Nov/2008 – March/2009 |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
Customer/Agency |
Department of Defense, Department of the Army |
Location |
Fort Myer, VA |
Project Type |
Design/Build Construction |
Contract Value |
$160,000 |
Contract Number |
W91QF7-08-C-0025 |
CFM Project
Manager |
Mr. Tim Stufft |
CFM Construction
Manager |
Mr. Dennis Weidner |
Project Title |
Building 238 Boiler Replacement |
Description of Project |
CFM Engineering provided all design, labor, materials, and Project and Construction Management services for the replacement of Building 238 boiler room. Scope includes demolition of existing equipment and all new equipment, controls, tanks, and civil work. |
Period of Performance |
Nov/2008 – May/2009 |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
Customer/Agency |
Smithsonian Institute, Washington DC |
Location |
Museum of Natural History |
Project Type |
Construction Services |
Contract Value |
$1,200,000 |
Contract Number |
F07CC10283 |
CFM Project
Manager |
Mr. Tim Stufft |
CFM Construction
Manager |
Mr. Michael Schumacher |
Project Title |
West Wing Penthouse Mechanical Systems Replacement |
Description of Project |
CFM Engineering provided all labor, materials, and Project and Construction Management services for the Mechanical Systems Upgrade for the Museum of Natural History. Scope includes all air handler equipment, electrical services, and installation related construction services. |
Period of Performance |
Feb/2009 – June/2009 |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
|
Customer/Agency |
Environmental Protection Agency (EPA) |
Location |
Fort Meade, MD |
Project Type |
Laboratory Renovation |
Contract Value |
$143,000 |
Contract Number |
EP-C-08-023 |
CFM Project
Manager |
Mrs. Nancy Fitzgerald |
CFM Construction
Manager |
Mr. Dennis Weidner |
Project Title |
Chemical Warfare Agent Laboratory Renovation |
Description of Project |
CFM Engineering provided all labor, materials, and Project and Construction Management services for the Laboratory renovation/upgrade of interior space including fume hood, electrical systems, and mechanical (HVAC) systems. |
Period of Performance |
Feb/2008 – May/2008 |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
Customer/Agency |
Department of the Army, US Army Corps of Engineers, Baltimore District |
Location |
Walter Reed Army Hospital |
Project Type |
Design/Build Construction Services |
Contract Value |
$670,000 |
Contract Number |
W912DR-08-C-0068 |
CFM Project
Manager |
Mrs. Ruth Heffes |
CFM Construction
Manager |
Mr. Michael Schumacher |
Project Title |
Renovations - Mologne House and Fisher Houses I, II, III |
Description of Project |
CFM Engineering providing all design, labor, materials, and Project and Construction Management services for the Internal/External renovations of four (4) building @ Walter Reed Army Hospital. Scope includes civil works, fire alarm controls, HVAC upgrades, interior renovations, and external renovations. |
Period of Performance |
Dec/2008 – Sept/2009 |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
Customer/Agency |
Department of Defense, Department of the Army |
Location |
Fort Myer, VA |
Project Type |
Project Management Services |
Contract Value |
$91,000 |
Contract Number |
Subcontractor |
CFM Project
Manager |
Mr. Tim Stufft |
CFM Construction
Manager |
|
Project Title |
Mechanical Assessment and Upgrade Recommendations of Barracks HVAC Systems |
Description of Project |
CFM Engineering provided Engineering and Mechanical assessment and recommendations for HVAC systems upgrades of barracks and steam press rooms. |
Period of Performance |
2007 – 2008 |
Prime or Subcontractor |
Subcontractor (Prime Contractor: Kellogg, Brown & Root Corporation) |
Bonded |
No |
|
| |
Customer/Agency |
Smithsonian Institute |
Location |
Suitland, MD |
Project Type |
Construction Services |
Contract Value |
$91,000 |
Contract Number |
Subcontractor |
CFM Project
Manager |
Mr. Barry Barker |
CFM Construction
Manager |
Mr. Michael Schumacher |
Project Title |
Native American CRC HVAC Upgrade |
Description of Project |
CFM Engineering provided all labor, materials, and Project and Construction Management services for the Installation of 20-Ton HVAC computer room unit at CRC facility. Project scope included all flora/fauna preservation of exterior areas. |
Period of Performance |
Oct/2007 – Dec/2007 |
Prime or Subcontractor |
Subcontractor (Prime Contractor: Kellogg, Brown & Root Corporation) |
Bonded |
No |
|
| |
Customer/Agency |
Department of Health & Human Services, National Institutes of Health |
Location |
Bethesda, MD |
Project Type |
Project Management Services |
Contract Value |
$165,000 |
Contract Number |
Subcontractor |
CFM Project
Manager |
Mr. Tim Stufft |
CFM Construction
Manager |
|
Project Title |
HVAC Upgrade, Incunabula Building 36 |
Description of Project |
CFM Engineering provided all Project Management services for the Mechanical HVAC systems upgrade for the Building 36 library. |
Period of Performance |
Jan/2008 – April/2008 |
Prime or Subcontractor |
Subcontractor (Prime Contractor: Kellogg, Brown & Root Corporation) |
Bonded |
No |
|
| |
Customer/Agency |
Department of the Army, US Army Corps of Engineers, Baltimore District |
Location |
Defense Depot
Susquehanna, PA |
Project Type |
Design/Build Electrical and Energy Conservation Services |
Contract Value |
$1,950,000 |
Contract Number |
W912DR-09-D-0022 |
CFM Project
Manager |
Mrs. Ruth Heffes |
CFM Construction
Manager |
Mr. Brian LaHatte |
Project Title |
Energy Improvement Project, DDSP, New Cumberland, PA |
Description of Project |
CFM Engineering providing design, labor, materials, and Project and Construction Management services for electrical systems upgrade for five (5) defense storage warehouses totaling over 1.0 MM square feet. |
Period of Performance |
March/2009 – Present |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
Customer/Agency |
Smithsonian Institute, Garber Facility |
Location |
Suitland, MD |
Project Type |
Construction Services |
Contract Value |
$43,000 |
Contract Number |
F07CC10283 |
CFM Project
Manager |
Mrs. Nancy Fitzgerald |
CFM Construction
Manager |
Mr. Edwin Bautista |
Project Title |
Bldg 12 Dry Fire Suppression Upgrade |
Description of Project |
CFM Engineering provided labor, materials, and Project and Construction Management services for the installation of dry fire suppression system. |
Period of Performance |
Sept/2008 – Jan/2009 |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
Customer/Agency |
Department of Defense, Department of the Army |
Location |
Fort Detrick, MD |
Project Type |
Construction Services |
Contract Value |
$27,000 |
Contract Number |
W81XWH-08-T-0267 |
CFM Project
Manager |
Mrs. Nancy Fitzgerald |
CFM Construction
Manager |
Mr. Dennis Weidner |
Project Title |
Oct/2008 – Feb/2009 |
Description of Project |
CFM Engineering provided all labor, materials, and Project and Construction Management services for the Interior Painting of Building 524 & Professional Surveying of Bldg 844 |
Period of Performance |
Oct/2008 – Feb/2009 |
Prime or Subcontractor |
Prime Contractor |
Bonded |
No |
|
| |
Customer/ Agency |
Smithsonian Institute, Suitland, MD |
Location |
Garber Facility |
Project Type |
Construction Services |
Contract Value |
$2,000,000 |
Contract Number |
F09SOL0058 |
CFM Project
Manager |
Mr. Tim Stufft |
CFM Construction
Manager |
Mr. Brian LaHatte |
Project Title |
Backflow Prevention and Mechanical Piping Installation |
Description of Project |
CFM Engineering to provide all labor, materials, and Project and Construction Management services for the installation of underground fire water and potable water lines and associated equipment. Project scope includes installation of all building backflow prevention systems. |
Period of Performance |
Current |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
Customer/Agency |
Department of Defense, Department of the Army |
Location |
Fort Detrick, MD |
Project Type |
Construction Services |
Contract Value |
$61,000 |
Contract Number |
W81XWH-09-Q-0011 |
CFM Project
Manager |
Mrs. Ruth Heffes |
CFM Construction
Manager |
Mr. Dennis Weidner |
Project Title |
Building 190 Automatic Security Gate |
Description of Project |
CFM Engineering providing all labor, materials, and Project and Construction Management services for the installation of Building 190 Security Gate and Video Monitoring System. |
Period of Performance |
Current |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
Customer/Agency |
Department of Commerce (NOAA) |
Location |
Oxford, MD |
Project Type |
Design/Build Renovation Services |
Contract Value |
$132,000 |
Contract Number |
WC133C-09-SE-4409 |
CFM Project
Manager |
Mr. Barry Barker |
CFM Construction
Manager |
Mr. Dennis Weidner |
Project Title |
Necropsy Laboratory Design/Build Renovation |
Description of Project |
CFM Engineering provided all design, engineering, labor, materials, Project and Construction Management services for interior renovation of the Necropsy Laboratory. Project scope includes demolition, interiors, laboratory equipment including fume hoods, and commissioning services. |
Period of Performance |
Sept/2009 – April/2010 |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
| State Construction |
Customer/Agency |
Maryland Environmental Services |
Location |
Brown Station Landfill
Prince George County, MD |
Project Type |
Construction Services |
Contract Value |
$163,000 |
Contract Number |
07-05-59 |
CFM Project
Manager |
Mr. Kevin Fitzgerald |
CFM Construction Manager |
Mr. Dennis Weidner |
Project Title |
Pre-Engineered Trailer Installation |
Description of Project |
CFM Engineering provided all labor, materials, Project and Construction Management services for the installation of a pre-engineered modular trailer. Scope of work included all water & wastewater piping, electrical wiring, data wiring and civil/foundation requirements. |
Period of Performance |
May/2008 – April/2009 |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
Customer/Agency |
Anne Arundel Community College |
Location |
Arnold, MD |
Project Type |
Construction Services |
Contract Value |
$265,000 |
Contract Number |
C200803A |
CFM Project
Manager |
Mr. Kevin Fitzgerald |
CFM Construction Manager |
Mr. Rick Martinez |
Project Title |
Ceramics Laboratory & Classroom Renovation |
Description of Project |
CFM Engineering provided all labor, materials, and General Contracting services for the renovation/upgrade of college classroom. Scope of work included all laboratory equipment, interior areas, electrical systems, fire suppression systems as well as bathrooms. |
Period of Performance |
Oct/2007 – Jan/2008 |
Prime or Subcontractor |
Prime Contractor |
Bonded |
Yes |
|
| |
| Private Projects |
Customer/ Agency |
Bioreliance Corporation |
Location |
Rockville, MD |
Project Type |
General Contracting Services |
Contract Value |
$325,000 |
Contract Number |
BPO |
CFM Project
Manager |
Mrs. Nancy Fitzgerald |
CFM Construction
Manager |
Mr. Dennis Weidner |
Project Title |
Laboratory Clean Room Renovation |
Description of Project |
Construction and Project Management services for the upgrade of GMP Clean Room and offices for a biotech manufacturer. Scope included all interior space, mechanical systems, electrical systems, and freezers. |
Period of Performance |
2006 |
Prime or Subcontractor |
Prime Contractor |
Bonding |
No |
|
| |
Customer/ Agency |
Qiagen Corporation |
Location |
Rockville, MD |
Project Type |
Construction Services |
Contract Value |
Not Disclosed |
Contract Number |
BPO |
CFM Project
Manager |
Mrs. Nancy Fitzgerald |
CFM Construction
Manager |
Mr. Dennis Weidner |
Project Title |
Project/Construction Management Services |
Description of Project |
CFM Engineering provided labor and Project/Construction management services for various facilities and building project upgrades. These included: Boiler System and Feedwater System Replacement. Laboratory Clean Room Renovations. Metrology Services. Office Renovations. |
Period of Performance |
2007 – 2008 |
Prime or Subcontractor |
Prime Contractor |
|
| |
Customer/Agency |
Invitrogen Corporation |
Location |
Frederick, MD |
Project Type |
Design/Build Construction |
Contract Value |
$735,000 |
Contract Number |
39926-08-00100 |
CFM Project
Manager |
Mr. Barry Barker |
CFM Construction
Manager |
Mr. Dennis Weidner |
Project Title |
Innovation Center |
Description of Project |
CFM Engineering provided labor and General Contracting services for the design and construction renovations of approximately 6,000 square foot office and technology center. Scope included demolition of existing site and systems and renovations of all interior space, mechanical, fire, electrical, flooring, and data systems. |
Period of Performance |
May/2008 – Feb/2009 |
Prime or Subcontractor |
Prime Contractor |
Bonding |
No |
|
|
| |
Customer/Agency |
Invitrogen Corporation |
Location |
Frederick, MD |
Project Type |
Construction Services |
Contract Value |
$275,000 |
Contract Number |
BPO |
CFM Project
Manager |
Mr. Kevin Fitzgerald |
CFM Construction
Manager |
Mr. Sam Hood |
Project Title |
Cell Culture Laboratory Renovation |
Description of Project |
CFM Engineering provided all labor and General Contracting services for the construction renovations for biotech laboratory. Scope of work included all mechanical and electrical systems as well as interior renovations and flooring. |
Period of Performance |
Aug/2007 – Dec/2007 |
Prime or Subcontractor |
Prime Contractor |
Bonding |
No |
|
| |
Customer/Agency |
Washington Gas |
Location |
Beltsville, MD |
Project Type |
Construction Services |
Contract Value |
$550,000 |
Contract Number |
BPO |
CFM Project
Manager |
Mr. Kevin Fitzgerald |
CFM Construction
Manager |
Mr. Rick Martinez |
Project Title |
Boiler Feedwater Systems Upgrade |
Description of Project |
CFM Engineering provided labor and Project & Construction Management Services for the installation of a new boiler feedwater system for the Washington Gas, Ravenswood Facility. Project scope included all piping, valving, tankage, meters, controls, and electrical systems. |
Period of Performance |
2005 |
Prime or Subcontractor |
Prime Contractor |
|
| |
Customer/Agency |
Baxter Pharmaceuticals |
Location |
Rockville, MD |
Project Type |
Engineering Services |
Contract Value |
Not Disclosed |
Contract Number |
BPO |
CFM Project
Manager |
Mr. Kevin Fitzgerald, PE |
CFM Site
Leader |
Mr. Edwin Bautista |
Project Title |
Project Engineering Services |
Description of Project |
CFM Engineering providing at-site Engineering Personnel for site services and Project Management Services. Services scope includes all building, utilities, process, and manufacturing systems. |
Period of Performance |
June/2008 – Present |
Prime or Subcontractor |
Prime Contractor |
|
| |
Customer/Agency |
Sparrows Point Steel, Maryland |
Location |
Sparrows Point, MD |
Project Type |
Environmental Services |
Contract Value |
$41,000 |
Contract Number |
BPO |
CFM Project
Manager |
Mr. Chris Izydore |
|
|
Project Title |
Blast Furnace Cold Well Basin Sludge Management |
Description of Project |
CFM Engineering provided labor and Project Management services for the removal, dewatering, and disposal of Cold Well Basin sludge. Project scope included provision of pumping equipment, storage, and disposal of Geotube dewatering bags. |
Period of Performance |
Sept/07 – Nov/07 |
Prime or Subcontractor |
Prime Contractor |
|
| |
Customer/ Agency |
Acambis Corporation |
Location |
Rockville, MD |
Project Type |
Engineering/Process Control Svc’s |
Contract Value |
Not Disclosed |
Contract Number |
BPO |
CFM Project
Manager |
Mr. Tim Stufft |
CFM Site
Leader |
Mr. Joseph Schumacher |
Project Title |
On-Site Engineering and Controls Services |
Description of Project |
CFM Engineering provided on-site Process Engineering and Process Controls specialists to support plant construction and start-up of manufacturing systems. |
Period of Performance |
2007 – 2008 |
Prime or Subcontractor |
Prime Contractor |
|
| |
|
|
|